ROW PROJECT NAME YEAR DURATION STATUS CLIENT
1
Precomm. & Commissioning of 12B Platform
2014 6 COMPLITED IOEC
2 Precomm. & Commissioning of 18A Platform 2014 3 COMPLITED IOEC
 3 Yard Pre-comm & Commissioning of Phase 19 2015 3 COMPLITED IOEC
 4 Sand blast and painting Phase 17 Platforms and Flare and Phase 18 Platform 2015 3 COMPLITED IOEC
 5 Pservation SPD-17Are 2015 12 COMPLITED IOEC
 6
Operation and Maintenance Phase 12 Platforms
2014 12 COMPLITED IOEC
 7 Pre-comm. Commissioning and Hookup of SPD19C 2016 18 COMPLITED IOEC
 8 Precomm. & Commissioning of 17A Platform 2015 6 COMPLITED IOEC
 9 Yard Pre-comm & Commissioning of Phase 20&21 2015 8 COMPLITED IOEC
 10 Operation and Maintenance Phase 17&18 Platforms 2014 12 COMPLITED IOEC
 11 Pre-comm. Commissioning and Hookup of SPD19A 2016 18 COMPLITED IOEC
 12 Pre-comm. Commissioning and Hookup of SPD21 2016 9 COMPLITED IOEC
 13 Operation and Maintenance SPD19C 2017 6 COMPLITED IOEC
 14
Precomm. & Commissioning of SPD20
2016 6 COMPLITED IOEC
 15 Pre-comm. Commissioning and Hookup of SPD19B 2016 4 COMPLITED IOEC
 16 Operation and Maintenance SPD19A 2016 7 COMPLITED IOEC
 17 Operation and Maintenance SPD21 2016 12 COMPLITED IOEC
18 Operation and Maintenance SPD20 2016 6 COMPLITED IOEC
 19
Pre-commissioning of Phase 14 Pipelines
2017 12 COMPLITED IOEC
 20 Construction and Pre-commissioning of Phase 22-24 Pipelines 2017 18 COMPLITED IOEC
 21 Phase 19 SPM and Telemetry Pre-comm. And Commissioning 2021 2 COMPLITED IOEC
 22 South Pars Gas Field Diesel Generator Overhaul 2020 24 ONGOING POGC
 23 Pre-commissioning of Phase 13 Pipelines 2018 12 ONGOING KITO
 24 Pre-commissioning of Phase 13 Pipelines 2019 1 ONGOING IOEC
25 Sarkhoun Qeshm Refinary Preservation and Maintenance 2019 12 COMPLITED IOEC
26 SPD20 , 21 Punch Clearance 2017 2 COMPLITED IOEC
 27 Phase 13,14,23 Spool Fabrication 2018 9 COMPLITED IOEC
28 Phase 13,14,23 Pipelines Pre-commissioning 2019 26 COMPLITED IOEC
29 Wreck Removal, Renovation and Re-commissioning SPD9 Platform 2019 12 COMPLITED IOEC
30 Pre-commissioning of Phase 16 Pipelines 2020 6 COMPLITED IOEC
31 Phase 16 Spool Fabrication 2020 3 COMPLITED  IOEC
32 Removing of Drilling Temporary Wallson Spp14B 2020 1 COMPLITED IOEC
33 Construction and Pre-commissioning of Phase 19 Pipelines 2020 6 COMPLITED IOEC
34 Jask Onshore Pipeline Construction, Installation and Commissioning 2020 24 COMPLITED IOEC
35 Remaining works of Drilling Activities on SPD14 B&D 2020 3 COMPLITED IOEC
36 Sarkhoun Qeshm Refinary Preservation and Maintenance 2019 12 COMPLITED IOEC