PARS OIL AND GAS COMPANY as subsidiary of NIOC intends to develop an International Export (& Import) oil terminal in 60km of North West of Jask in order to transfer of Iranian export crude oil (heavy & light) and gas condensate. Crude oil/Condensate will be exported / imported through three identical SPMs each with capacity of 11,000 m3/hr via three set of 36″ pipelines. Offshore pipelines will be arranged as a loop to send and receive pigs from onshore so each SPM will be connected to shore terminal via 2×36” subsea pipelines. The main goal of this terminal is to export 365 million barrels per year of crude oil/ condensate from storage area with capacity of 10,000,000 BBL and through subsea pipelines and single point mooring system (SPMs). Onshore terminal facilities shall be capable of receiving crude oil/ condensate from SPM and offshore pipelines as well. In order to achieve project target all equipment’s such as custody metering stations, pigging launchers and receivers, control room, buildings and other facilities which are necessary to be considered. Also, there shall be a break water including supporting port to be a shelter area for tug boats and supporting vessels needed for terminal marine operation & marine facilities maintenance.
Handling, Construction, Installation, Hydrotesting, Pre Commissioning, Commissioning, and Start-up of three set of 36″ pipelines in order to export and import of Iranian crude oil (heavy & light) and condensate connecting landfall point to Jask Terminal Onshore oil Treatment Plant inlet facilities with approximate length of 3000 m (total), including Insulating Joint Pits, Insulating Joint, Anchor Block, Pig Launcher/ Receiver, Valves, etc.
Work Summary:
1- Line 1-2-3-4-5-6 Pipeline Surveying and Alignment and Leveling are performed to Volume 1453 ML.
2- Line 1-2-3-4-5-6 Pipeline Fit-up are performed to Volume 8832 Dia-inch.
3- Line 1-2-3-4-5-6 Pipeline Welding are performed to Volume 8648 Dia-inch.
4- Line 1-2-3-4-5-6 Pipeline NDT are performed to Volume 7220 Dia-inch.
5- Line 1-2-3-4-5-6 UG Pipeline Holiday Test are performed to Volume 65 Joint.
6- Line 1-2-3-4-5-6 Pipeline Sandfill & Backfill are performed to Volume 10176 m3.
7- Line 1-2-3-4-5-6 Pipeline Excavation are performed to Volume 32421 m3.
8- Line 1 Pre-comm is performed and is ready for Start-up.
The Physical % Complete of Project up to now is 74.31%.